GLOBAL IMPLEMENTATION FOR A JAPANESE CHEMICAL COMPANY
Oracle JD Edwards EnterpriseOne
COMPANY OVERVIEW
Nicca Chemical is a chemical manufacturer that develops for the various industries, including the textile industry, based on surfactant science. Nicca Japan decided to go global with JD Edwards to its subsidiary in the US.
1. The Challenge
- Risks due to time zone difference between Japan and US.
- Business parallel objective besides JD Edwards implementation: New business best practices and standardization had to be applied in US subsidiary, leaving the idea of a simple rollout bit behind.
- Many implementation teams had to be aligned and communicate well during the project, and many business decission makers: Nicca Japan, Japanese JDE vendor, Nicca US, ITCROSS team.
- New business global rules were issued in the middle of the project, and had to be analyzed and applied in Nicca USA, changing project scope and timeline.
- Language barrier between HQ in Japan and US team.
2. Why ITCROSS
- Experience with US customers in the chemical industry, and global implementation expertise.
- Credentials working the Japanese vendor and team.
- Delivery team in US time zone and attractive cost-benefit.
3. The Outcomes
- Successful JD Edwards implementation, and new business processes standards applied to US location.
- First of 14 global sites at Nicca to complete the implementation.
- Beat the time zone difference, and achieved a double-shift service to the customer in Japan and in the US.
- Overcame language barrier, due to bilingual qualified team of consultants.
- Supported Nicca US team after the implementation successfully.
“ITCROSS came into our implementation, midway through the project, facing significant challenges in order to achieve the required outcome. With a staff of experienced project managers and JDE developers, ITCROSS quickly got our implementation back on track and led us to a successful Go Live. Working remotely from Argentina, ITCROSS staff were available 24/7 and formed the close relationships with our team needed for his type of project. We were the first company out of 14 sites in our global organization to succeed! ITCROSS was there for us during implementation and are still there for us as we continue to run JDE EnterpriseOne”.
Brian MooreIT Manager Nicca US